Date Region Substation Transformer (MVA) Feeder MYTO Feeder Disco 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Min Avg Max
12 Feb 2026 None MINNA TS TRI- 60MVA FUT FDR 132KV MINNA TS_33KV FUT FDR_PL_PL ABUJA 0.3 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.5 0.8 0.7 0.8 0.4 0.8 0.6 0.8 0.3 0.2 0.3 0.3 0.5 NCL/A - 0.1 0.354166666666667 None
12 Feb 2026 None B/KEBBI TS TR4-60MVA GAYA — KADUNA 4.3 4.1 4.2 4 4.8 5 0 0 5.6 5.4 2.7 2.8 2.9 2.7 4.3 4.1 4.1 0.1 3.2 4.1 4 0.1 0.1 - 0 2.83333333333333 None
12 Feb 2026 None BIDA TR2-30MVA GRA 11kv fdr — ABUJA LSD 5 4.9 EMR EMR EMR EMR EMR EMR EMR EMR EMR 6.3 6.6 6.7 6.7 LSD LSD LSD LSD LSD LSD NCL/A - 6.3 1.09583333333333 None
12 Feb 2026 None B/KEBBI TS TR4-60MVA GWANDU — KADUNA 0.2 0.2 0.2 0.2 0.2 0.3 0.4 0.5 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.4 0.5 0.6 0.6 0.6 0.6 0.5 - 0.2 0.3875 None
12 Feb 2026 None KAINJI 132KV TR1- 40MVA HYDROPOLIS 1 — IBADAN 0.16 0.17 0.18 0.18 0.19 0.21 0.91 0.19 0.19 0.19 0.17 0.19 0.2 0.18 0.2 0.19 0.19 0.19 0.19 0.18 0.19 0.2 0.19 - 0.17 0.20375 None
12 Feb 2026 None KAINJI 132KV TR2- 40MVA HYDROPOLIS 2 — BILATERAL 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.08 0.09 0.1 0.09 0.09 0.09 0.08 0.1 0.09 0.09 0.1 0.09 0.09 0.09 0.07 - nan nan None
12 Feb 2026 None JEBBA TR1- 30MVA J/Bachita — IBADAN 9.5 9.35 6.2 8.8 9.35 11 3.7 4.15 4.45 3.95 6.1 9.95 10.3 10.25 6.8 6.8 7.55 8.25 10.9 9.7 8.95 10.25 9.2 - 3.7 7.33125 None
12 Feb 2026 None B/KEBBI TS TR4-60MVA JEGA — KADUNA - - - - - - - - - - - - - - - - - - - - - - - - 0 0 None
12 Feb 2026 None MINNA TS TR2- 30MVA KATEREGI FDR 132KV MINNA TS_33KV KATAREGI FDR_PL_PL ABUJA NCL/A NCL/A NCL/A NCL/A O/C O/C O/C O/C O/C O/C O/C O/C O/C 6.2 OC/EF 6.3 6.1 NC L/A NC L/A NC L/A NC L/A NC L/A NCL/A - 6.1 0.775 None
12 Feb 2026 None YAURI TR2-40MVA KOKO — KADUNA DS DS DS DS DS DS DS DS DS DS DS DS DS DS DS DS DS DS DS DS 3.5 3.7 3.7 - 3.5 0.6 None
12 Feb 2026 None SHIRORO2 TR1- 30MVA KUTA/GWADA 132KV SHIRORO TS_33KV GWADA FDR_PL_PL ABUJA 3.8 3.6 3.4 3.4 3.6 4.2 5.5 5.8 E/F 4.8 6.3 6.6 6.5 EF/OC EF/OC EF/OC EF/OC EF/OC EF/OC EF/OC 4.7 6.3 NCL/A - 3.4 2.54583333333333 None
12 Feb 2026 None BIDA TR2-30MVA KUTIGI 132KV BIDA TS_33KV KUTIGI FDR_PL_PL ABUJA O/C&EF 2.2 2.6 2.5 2.7 2.9 0.05 0.05 2.9 2.6 2.9 NCL/A NCL/A NCL/A NCL/A NCL/A NCL/A NCL/A NCL/A NCL/A NCL/A NCL/A NCL/A - 0.05 0.8 None
12 Feb 2026 None SOKOTO TR 3 60MVA KWARE — KADUNA 2.6 2.5 2.6 2.3 2.2 2.4 2.7 0.8 1.8 2.1 2.2 2.1 2.1 0.6 0.7 0.7 0.8 EMR EMR EMR EMR EMR EMR - 0.6 1.0875 None
12 Feb 2026 None B/KEBBI TS TR5-60MVA LABANA — KADUNA 0 0 0 0.1 0 0 0.1 0 0.1 0.3 0.3 0.4 0.4 0.4 0.4 0.4 0.4 0.1 0 0 0 0 0 - 0 0.141666666666667 None
12 Feb 2026 None MINNA TS TRI- 60MVA LAPAI FDR 132KV MINNA TS_33KV LAPAI FDR_PL_PL ABUJA NCL/A NCL/A NCL/A NCL/A NCL/A NCL/A NC L/A NC L/A NC L/A NC L/A NC L/A NC L/A NC L/A NC L/A NC L/A NC L/A NC L/A NC L/A NC L/A NC L/A NC L/A NC L/A NCL/A - 0 0 None
12 Feb 2026 None BIDA TR2-30MVA LEMU 132KV BIDA TS_33KV LEMU FDR_PL_PL ABUJA 0.4 0.4 O/C&EF O/C&EF O/C&EF O/C&EF O/C&EF O/C&EF 0.8 4.8 0.2 4.8 OC&EF OC&EF OC&EF OC&EF OC&EF 2.6 4.6 NCL/A NCL/A NCL/A NCL/A - 0.2 0.741666666666667 None
12 Feb 2026 None JEBBA TR1- 30MVA Life Camp — IBADAN 0.55 0.55 0.55 0.5 0.55 0.7 0.7 0.5 0.55 0.5 0.5 0.5 0.55 0.55 0.55 0.6 0.65 0.6 0.7 0.75 0.75 0.7 0.6 - 0.5 0.545833333333333 None
12 Feb 2026 None MINNA TS TR2- 30MVA M/KUNKEL0DR — ABUJA 6.1 5.8 5.8 6 3.1 4.5 2 1.9 O/C 2.9 3.2 NC L/A NC L/A NC L/A NC L/A 3.5 3.5 3.2 2.6 2.4 2.4 2.2 2.2 - 1.9 2.22916666666667 None
12 Feb 2026 None KONTAGORA TR1- 60MVA MASUGA FDR — ABUJA 0 0 0.01 0 0.01 0.01 0 0.02 0.05 0.04 0.07 0.09 0.09 0.08 0.1 0.08 0.07 0.14 0.05 0.05 0.05 0.09 0.09 - nan nan None
12 Feb 2026 None JEBBA TR1- 30MVA Mokwa — IBADAN 2.95 7 8.5 8.05 4.15 4.15 8.25 8 7.35 7.25 1.8 1.85 1.8 2.45 2.5 2.45 3.2 3.15 2.85 2.85 9.2 3.5 3.3 - 1.8 4.19375 None
12 Feb 2026 None BIDA TR5-60MVA NEW AGAIE 132KV BIDA TS_33KV NEW AGAIE FDR_PL_PL ABUJA 0.1 0.1 2.5 2.5 2.7 2.9 0.1 0.1 2.6 2.7 0.1 0.1 OC OC OC OC OC OC OC OC OC OC NCL/A - 0.1 0.679166666666667 None
12 Feb 2026 None SOKOTO TR 3 60MVA NEW INJECTION — KADUNA 7.2 7.3 5.6 4.3 7.9 0.5 0.7 0.5 6.1 6.3 6.3 8.4 6.4 5.9 5.8 5.6 5.6 1.2 1.1 0.8 0.8 0.7 1.2 - 0.5 3.45416666666667 None
12 Feb 2026 None YAURI TR1-40MVA NGASKI — KADUNA DS DS DS DS DS DS DS 2.9 2.9 DS DS DS DS DS DS DS DS DS DS DS OC/EF OC/EF DS - 2.9 0.241666666666667 None
12 Feb 2026 None MINNA TS TRI- 60MVA NNPC/WW FDR 132KV MINNA TS_33KV NNPC FDR_PL_PL ABUJA 2.5 2.3 2.4 2.1 2.3 2.2 2.5 1.9 2.6 5 5.4 5.4 4.8 4.6 3.6 NC L/A NC L/A NC L/A NC L/A 2.6 2.5 3 NCL/A - 1.9 2.20416666666667 None
12 Feb 2026 None OKPELLA TS T1(15MVA)&T2(60MVA) OKPELLA TOWN — BEDC 3.2 3 3 3.2 3.8 4.1 4.1 3.8 0.3 0.2 2.3 3.7 4.5 4.9 5 5 1.3 1.3 1.5 3.2 1.4 1.2 1.2 2.6 0.2 2.825 None
12 Feb 2026 None MINNA TS TR7- 60MVA P/ HOUSE — ABUJA 8.1 7.7 7.5 7.5 8.1 0.8 1 1.3 4.4 4.8 4.8 4.9 2 1.8 1.7 1.5 1.3 1.2 1.2 1.2 2.2 2.2 2.1 - 0.8 2.73333333333333 None
12 Feb 2026 None SOKOTO TR1- 40/30MVA P/STATN — KADUNA 6.1 6 6.1 6.1 12.3 8.5 12.5 11.4 14.8 14.9 10.8 3.4 3.5 9 9.1 8.8 8.8 3.5 3.5 3.2 3.1 2.9 2.5 - 2.4 6.7125 None
12 Feb 2026 None 132KV KATAMPE-2 TS TR1- 100MVA SPARE-II FDR — AEDC - - - - - - - - - - - - - - - - - - - - - - - - 0 nan None
12 Feb 2026 None AJAOKUTA TS T1- 30MVA STEELPLANT — AEDC 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.3 0.4 0.5 0.4 0.1 0.2 0.2 0.5 0.5 0.3 0.2 0.1 0.3 0.3 0.2 0.2 0.2 0.1 0.233333333333333 None
12 Feb 2026 None B/KEBBI TS TR6-100MVA TAMBUWAL — KADUNA 1.5 1.4 1.4 1.4 1.4 1.5 1.8 1.8 1.7 1.6 INST.E/F 0.5 2.5 2.4 0.5 0.4 0.4 0.1 0.4 3.5 1.7 1.8 1.8 - 0.1 1.25833333333333 None
12 Feb 2026 None KONTAGORA TR1- 60MVA TOWN 132KV KONTAGORA TS_33KV TOWN FDR_PL_PL ABUJA 5 8.9 5.3 5.3 5.5 4.9 6.1 5.9 6 6.5 6.4 6.2 6.1 5.8 6.1 6.1 11.1 6.5 6.2 2.6 6.7 5.5 5.8 - 2.6 5.5125 None
12 Feb 2026 None SOKOTO TR 3 60MVA TOWN 132KV KONTAGORA TS_33KV TOWN FDR_PL_PL KADUNA 6.3 6.2 5.6 0.3 0.3 0.3 0.3 0.3 0.3 0.4 0.4 7.8 7.5 4.7 4.7 7.3 7.4 0.1 0.1 0.4 0.5 0.4 0.4 - 0.1 2.075 None
12 Feb 2026 None BIDA TR5-60MVA Town 11KV fdr — ABUJA 7.4 6.8 6.7 6.7 7.3 LSD LSD LSD LSD LSD LSD LSD LSD LSD LSD LSD 8.9 LSD LSD LSD LSD LSD NCL/A - 6.7 1.23333333333333 None
12 Feb 2026 None B/KEBBI TS TR5-60MVA UNIVERSITY — KADUNA 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.2 0.3 0.4 0.5 0.5 0.5 0.4 0.4 0.2 0.2 0.4 0.7 0.6 0.5 0.3 - 0.2 0.3125 None
12 Feb 2026 None KONTAGORA TR1- 60MVA WATER WORKS 132KV KONTAGORA TS_33KV WATERWORKS FDR_PL_PL ABUJA 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.4 0.4 0.4 0.2 0.4 0.3 0.3 0.3 0.4 0.4 0.4 0.4 - 0.2 0.308333333333333 None
12 Feb 2026 None SOKOTO TR 3 60MVA YABO — KADUNA 2.8 2.8 2.7 2.7 2.7 3.2 NCL/A NCL/A NCL/A NCL/A NCL/A NCL/A 2.5 2.4 2.5 2.5 2.7 EMR EMR EMR EMR EMR EMR - 2.4 0.995833333333333 None
12 Feb 2026 None YAURI TR1-40MVA YAURI — KADUNA 3.4 3.5 3.8 3.7 3.7 3.5 DS DS DS DS DS DS DS 4 4 DS 3.7 3.6 DS DS DS DS DS - 3.5 1.25 None
12 Feb 2026 None MINNA TS TR7- 60MVA ZARUMAI FDR 132KV MINNA TS_33KV ZARUMAI FDR_PL_PL ABUJA 6.2 5.9 5.5 5.6 7 7.4 7.2 6.6 6.7 2.8 2.9 3 3.1 3.1 3.1 3.1 3 3.1 3.2 NCL/A NCL/A NCL/A NCL/A - 2.8 3.30833333333333 None
12 Feb 2026 None YAURI TR1-40MVA ZURU — KADUNA 2.2 1.8 1.8 1.8 1.8 1.8 2 2.3 2.5 2.8 2.8 2.8 5.5 NCL/A NCL/A DS 0.5 0.6 0.5 3 3 3 E/F - 0.5 1.7 None
11 Feb 2026 None MINNA TS TR4- 15MVA 11KV CHANCHAGA FDR — ABUJA LSD LSD LSD 6 6.5 7 8 7 6.6 5.2 LSD LSD LSD LSD LSD LSD LSD LSD LSD LSD LSD LSD LSD - 5.2 1.92916666666667 None
11 Feb 2026 None 132KV SULEJA TS TR1 - 7.5MVA 132/11KV 11KV DIKKO FDR — AEDC LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D 2 1.83 3 LS/D LS/D LS/D LS/D LS/D LS/D LS/D 1.83 2.27666666666667 None
11 Feb 2026 None 132KV SULEJA TS TR1 - 7.5MVA 132/11KV 11KV GAURAKA FDR — AEDC LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D 2.33 2.32 2.1 2 1.95 1.93 LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D 1.93 2.105 None
11 Feb 2026 None 132KV SULEJA TS TR1 - 7.5MVA 132/11KV 11KV MINNA RD FDR — AEDC LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D 5 4.33 3.67 3.67 4.33333333333333 None
11 Feb 2026 None 132KV SULEJA TS TR1 - 7.5MVA 132/11KV 11KV NNPC FDR — AEDC LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D I/S I/S I/S 0 nan None
11 Feb 2026 None MINNA TS TR3- 15MVA 11KV PARLFDR — ABUJA LSD LSD 6 7 7 LSD LSD LSD LSD LSD 8.2 8.5 LSD LSD LSD LSD LSD LSD LSD LSD LSD LSD LSD - 6 1.52916666666667 None
11 Feb 2026 None MINNA TS TR4- 15MVA 11KV SHIROROFDR — ABUJA LSD 3 3 3.2 3.5 3.5 LSD LSD 3.2 3.8 LSD LSD 3 3 LSD LSD LSD LSD LSD LSD LSD LSD LSD - 3 1.09166666666667 None
11 Feb 2026 None 132KV SULEJA TS TR1 - 7.5MVA 132/11KV 11KV WATER WORKS FDR — AEDC 0.67 0.67 0.67 0.73 0.8 0.42 LS/D LS/D LS/D LS/D 0.65 0.83 0.83 0.83 0.88 0.53 0.52 LS/D LS/D LS/D LS/D 0.47 0.6 0.5 0.42 0.6625 None
11 Feb 2026 None 132KV KATAMPE-1 TS TR2- 60MVA 33KV 9MOBILE FDR 132KV KATAMPE TS_33KV 9MOBILE FDR_PL_PL AEDC 1.4 1.4 1.3 1.3 1.3 1.4 1.4 1.5 1.7 1.7 1.9 1.8 1.8 1.9 1.9 1.9 1.1 1.7 1.7 1.7 1.6 1.6 1.6 1.6 1.1 1.59166666666667 None
11 Feb 2026 None 132KV SULEJA TS TR2- 45MVA 33KV ABUJA-STEEL FDR 132KV SULEJA TS_33KV ABUJA STEEL FDR_PL_PL AEDC I/S I/S I/S I/S 4 4.5 5 3.5 5 1 4 5 5 2.5 2.5 2.5 5 2.5 3.5 3.5 4.5 3.5 3.5 4.5 1 3.75 None
11 Feb 2026 None 132KV AKWANGA TS TR1- 40/30MVA 33KV AKWANGA FDR 132KV AKWANGA TS_33KV FDR 1 (AKWANGA FDR)_PL_PL AEDC 3.2 3 3 1.5 1.2 0.5 0.5 0.8 0.3 2.8 3.8 4 3.8 4 2.1 0.6 0.6 0.7 0.4 2.5 4.2 4 3.6 0.4 0.3 2.14583333333333 None
11 Feb 2026 None 132KV KEFFI TS TR1- 30MVA OR TR2-60MVA 33KV AVATAR FDR 132KV KEFFI TS_33KV AVATAR FDR_PL_PL AEDC 3.2 3.3 3.5 3.5 3.4 3.5 3.4 3.6 3.6 3.3 3.4 3.4 3.3 3.4 3.5 3.5 3.5 3.5 3.5 3.5 3.3 3.3 3.3 3.5 3.2 3.425 None
11 Feb 2026 None 132KV KUBWA TS TR2- 100MVA 33KV BWARI FDR 132KV KUBWA TS_33KV BWARI FDR_PL_PL AEDC LS/D LS/D LS/D LS/D 24.6 26.35 18.4 15.35 LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D 21.8 LS/G LS/G 15.35 21.3 None
11 Feb 2026 None 132KV KUBWA TS TR1- 60MVA 33KV DAM FDR 132KV KUBWA TS_33KV DAM FDR_PL_PL AEDC 0.55 0.55 0.55 0.55 0.6 0.75 0.75 0.7 0.6 0.6 0.4 0.6 0.6 0.4 0.5 0.6 0.6 0.8 0.9 1 0.8 0.7 0.7 0.6 0.4 0.641666666666667 None
11 Feb 2026 None 132KV KUBWA TS TR1- 60MVA 33KV DAWAKI FDR 132KV KUBWA TS_33KV DAWAKI FDR_PL_PL AEDC 12.8 12.05 11.4 11.1 LS/D LS/D 13.3 11.1 9.3 8.5 8.3 18.1 7.7 8.5 9.1 7.6 8 1 11.1 8.3 15.6 16 13.2 11.9 1 10.6340909090909 None
11 Feb 2026 None 132KV KUBWA TS TR1- 60MVA 33KV DEIDEI FDR 132KV KUBWA TS_33KV DEIDEI FDR_PL_PL AEDC 18.45 17.2 16.6 17 17.65 20 LS/D LS/D LS/D 17.4 16.7 16.5 16.5 16.5 L/SHED L/SHED 13.7 14.1 15.7 17.6 18.2 17.6 17.9 17.1 13.7 16.9684210526316 None
11 Feb 2026 None 132KV LAFIA TS TR1- 60MVA 33KV FDR A1 33OKV APIR-LAFIA LINE 1&2_132KV LAFIA TS_33KV 33KV FDR A1_PL_PL AEDC I/S I/S I/S I/S I/S I/S 0.4 0.5 0.3 0.5 0.5 0.4 0.4 0.5 0.4 0.5 0.5 I/S I/S I/S I/S I/S I/S I/S 0.3 0.445454545454545 None
11 Feb 2026 None 132KV LAFIA TS TR1- 60MVA 33KV FDR A2 33OKV APIR-LAFIA LINE 1&2_132KV LAFIA TS_33KV 33KV FDR A2_PL_PL AEDC 9 8.3 8.1 9.1 9.3 2.3 3.4 5.1 7.6 8.4 13.3 12.9 12.7 12.8 9.8 10 6.5 6.5 4.9 8.6 17 19.2 16.5 14.8 2.3 9.8375 None
11 Feb 2026 None 132KV LAFIA TS TR2- 60MVA 33KV FDR A5 33OKV APIR-LAFIA LINE 1&2_132KV LAFIA TS_33KV FDR A5_PL_PL AEDC 6.2 5.9 5.6 5.5 5.7 6.9 7.2 6.4 2.2 2.3 2.3 2.3 2.3 2.4 7.8 8.3 8.7 9.2 10 9.3 8.8 8 7.4 6.9 2.2 6.15 None
11 Feb 2026 None LOKOJA TS TR2-60MVA 33KV FDR 1 132KV CENTRAL AREA TS_33KV FDR 1_PL_PL AEDC 2.8 2.6 2.6 2.6 2.8 3.1 3.4 1.2 1.3 1.3 1.4 1.4 1.4 1.4 1.5 1.4 1.3 1.4 1.5 1.6 1.4 1.5 1.2 1.2 1.2 1.80416666666667 None
11 Feb 2026 None 132KV CENTRAL AREA TS TR1 - 100MVA 33KV FDR 1 132KV CENTRAL AREA TS_33KV FDR 1_PL_PL AEDC - - - - - - - - - - - - - - - - - - - - - - - - 0 nan None
11 Feb 2026 None LOKOJA TS TR2-60MVA 33KV FDR 2 132KV CENTRAL AREA TS_33KV FDR 2_PL_PL AEDC 16.6 21.2 21 21.3 5.9 i/s i/s 6.4 15 14.8 14 11 14.6 16.4 9.7 16.4 9.8 I/S I/S I/S 6.7 6.4 12.2 15.1 5.9 13.3947368421053 None
11 Feb 2026 None 132KV CENTRAL AREA TS TR1 - 100MVA 33KV FDR 2 132KV CENTRAL AREA TS_33KV FDR 2_PL_PL AEDC 4.79 4.59 4.35 4.41 5.17 6.11 4.8 6.51 8.41 9.2 10.44 10.47 9.94 10.42 9.83 9.76 9.5 6.46 6.99 3.58 6.17 5.92 6.66 5.46 3.58 7.08083333333333 None
11 Feb 2026 None LOKOJA TS TR2-60MVA 33KV FDR 3 132KV CENTRAL AREA TS_33KV FDR 3_PL_PL AEDC 3.6 3.4 3.3 3.2 3.3 3.3 3.4 3.6 4.1 4.6 4.9 5.1 5.1 5.2 5.2 4.8 4.5 4.4 EMERG 3.9 4.7 4.8 4.3 4 3.2 4.20434782608696 None
11 Feb 2026 None 132KV CENTRAL AREA TS TR1 - 100MVA 33KV FDR 3 132KV CENTRAL AREA TS_33KV FDR 3_PL_PL AEDC 9.99 9.43 10.23 9.38 9.95 12.01 9.37 12.41 12.76 14.97 16.94 14.2 15.77 17.8 13.31 11.79 15.22 14.91 15.21 8.91 13.37 12.96 14.82 11.95 8.91 12.8191666666667 None
11 Feb 2026 None 132KV CENTRAL AREA TS TR1 - 100MVA 33KV FDR 4 132KV CENTRAL AREA TS_33KV FDR 4_PL_PL AEDC 2.68 2.52 2.7 2.5 2.66 3.35 2.88 4.92 5.68 6.54 8.49 8.43 8.69 9.56 8.82 8.55 7.52 3.96 5.01 3.35 4.59 5.08 3.59 3.4 2.5 5.22791666666667 None
11 Feb 2026 None 132KV CENTRAL AREA TS TR2- 100MVA 33KV FDR 5 132KV CENTRAL AREA TS_33KV FDR 5_PL_PL AEDC 6.18 5.7 6.54 5.92 6.14 7.2 6.86 11.79 12.7 15.9 17.84 18.31 17.83 19.28 18.3 17.32 15.8 9.56 10.93 6.68 9.37 8.23 8.59 6.94 5.7 11.24625 None
11 Feb 2026 None 132KV CENTRAL AREA TS TR2- 100MVA 33KV FDR 6 132KV CENTRAL AREA TS_33KV FDR 6_PL_PL AEDC 14.4 12.55 14.05 12.98 14.37 17.29 14.64 18.65 15.53 16.9 19.08 18.97 21.24 27.18 24.38 24.4 24.32 22.54 19.58 8.7 12.61 11.97 19.35 16.46 8.7 17.5891666666667 None
11 Feb 2026 None 132KV CENTRAL AREA TS TR3-60MVA 33KV FDR 7 132KV CENTRAL AREA TS_33KV FDR 7_PL_PL AEDC - - - - - - - - - - - - - - - - - - - - - - - - 0 nan None
11 Feb 2026 None 132KV CENTRAL AREA TS TR3-60MVA 33KV FDR 8 132KV CENTRAL AREA TS_33KV FDR 8_PL_PL AEDC 13.39 13.07 14.49 12.76 12.03 15.93 12.38 14.54 9.98 17.04 15.91 20.31 17.57 22.26 18 17.97 20.44 22.05 22.26 13.74 19.7 21.58 21.72 18.35 9.98 16.9779166666667 None
11 Feb 2026 None 132KV CENTRAL AREA TS TR3-60MVA 33KV FDR 9 132KV CENTRAL AREA TS_33KV FDR 9_PL_PL AEDC - - - - - - - - - - - - - - - - - - - - - - - - 0 nan None
11 Feb 2026 None 132KV DAWAKI TS TR1 - 60MVA 33KV FDR D1 132KV GIS DAWAKI TS_33KV FDR D1_PL_PL AEDC 9.6 9.1 8.6 8.4 8.4 8.9 9.1 4.1 6.9 5.9 8.8 8.9 10.3 10.4 10.2 10.8 11 10.3 13.7 14.2 11.7 15.3 10.3 13.9 4.1 9.95 None
11 Feb 2026 None 132KV DAWAKI TS TR1 - 60MVA 33KV FDR D2 132KV GIS DAWAKI TS_33KV FDR D2_PL_PL AEDC 17.1 16 15.1 14.6 14.5 15.2 15 13.8 13.9 14 14.7 15.2 15.3 15.8 LS/T 6.7 13.4 13.8 NC 13.9 21.1 20.2 13.8 18.4 6.7 15.0681818181818 None
11 Feb 2026 None 132KV DAWAKI TS TR1 - 60MVA 33KV FDR D3 — AEDC - - - - - - - - - - - - - - - - - - - - - - - - 0 nan None
11 Feb 2026 None 132KV DAWAKI TS TR2- 60MVA 33KV FDR D4 — AEDC - - - - - - - - - - - - - - - - - - - - - - - - 0 nan None
11 Feb 2026 None 132KV DAWAKI TS TR2- 60MVA 33KV FDR D5 — AEDC I/S I/S I/S I/S I/S I/S I/S I/S 0.28 0.25 0.3 0.27 0.27 0.3 0.28 0.3 I/S I/S I/S I/S I/S I/S I/S I/S 0.25 0.28125 None
11 Feb 2026 None 132KV DAWAKI TS TR2- 60MVA 33KV FDR D6 132KV GIS DAWAKI TS_33KV FDR D6_PL_PL AEDC 1.37 1.29 1.18 1.15 1.14 1.16 1.13 0.95 0.77 0.81 0.78 SG SG 0.99 1.11 1.1 1.1 1.3 1.28 1.74 1.81 1.88 1.9 1.73 0.77 1.25772727272727 None
11 Feb 2026 None 132KV APO TS TR3- 100MVA 33KV FDR H1 132KV APO TS_33KV FDR H1_PL_PL AEDC 8.75 8.5 8.15 8.05 8.45 9.3 10.6 12.1 14.65 16.05 16.65 14.4 10.65 INST,OC/EF 13.6 12 9.9 10.4 11.05 10.8 10.7 9.1 8.7 9.3 8.05 10.95 None
11 Feb 2026 None 132KV APO TS TR1 60MVA 33KV FDR H11 132KV APO TS_33KV FDR H11_PL_PL AEDC 6.55 6.2 5.6 5.8 6.1 6.6 7.8 8.85 10.8 11.95 11.95 12.65 8.85 13.25 13.25 12.4 10.4 9.3 8.55 8.35 7.5 7.55 LS 6.55 5.6 8.99130434782609 None
11 Feb 2026 None 132KV APO TS TR1 60MVA 33KV FDR H13 132KV APO TS_33KV FDR H13 (JICA)_PL_PL AEDC 6 5.55 5.35 5.25 5.5 6.1 5.95 5.1 4.8 4.75 4.15 4.75 5 5.1 5.2 5.35 5.25 5.75 6.3 6.75 INST.EF/OC 5.95 7.2 LS 4.15 5.50454545454545 None
11 Feb 2026 None 132KV APO TS TR1 60MVA 33KV FDR H15 132KV APO TS_33KV FDR H15_PL_PL AEDC 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 None
11 Feb 2026 None 132KV APO TS TR3- 100MVA 33KV FDR H2 132KV APO TS_33KV FDR H2_PL_PL AEDC 4.8 4.55 4.3 4.25 4.15 4.45 4.8 5 5.4 6.05 6.2 6.55 4.6 6.45 6.75 6.65 6.4 5.05 4.85 5.55 5.3 5.3 5.05 4.85 4.15 5.30416666666667 None
11 Feb 2026 None 132KV APO TS TR3- 100MVA 33KV FDR H21 132KV APO TS_33KV FDR H21_PL_PL AEDC 10.55 16.1 14.6 13.9 19.05 20.6 14.85 12.85 11.75 6.4 LS LS LS 5.4 14.95 15.55 16.3 9.9 4 7.95 9.05 14.5 12.8 11.55 4 12.5047619047619 None
11 Feb 2026 None 132KV APO TS TR3- 100MVA 33KV FDR H23 132KV APO TS_33KV FDR H23_PL_PL AEDC 10 9.8 9.4 7.4 7.4 8.2 8 8 9.4 14.4 10 9.8 10.4 9.4 LS L/S L/S 8.6 9.4 9.6 10 10 9.6 12 7.4 9.56190476190476 None
11 Feb 2026 None 132KV APO TS TR3- 100MVA 33KV FDR H3 132KV APO TS_33KV FDR H3_PL_PL AEDC 13.8 12.9 11.9 11.75 11.8 13.2 9.95 16.2 18.8 LS 14.5 18.35 20.45 16.6 18.8 18.3 17.5 15 16.25 16.1 16.35 15.6 14.95 13.7 9.95 15.3369565217391 None
11 Feb 2026 None 132KV APO TS TR4- 100MVA 33KV FDR H31 132KV APO TS_33KV FDR H31_PL_PL AEDC 10.6 L/S 6.1 10.65 9.65 10.15 10.2 9.2 9.75 9.8 10 9.8 9.8 6.4 LS L/S 10.05 10 11.2 11.45 11.6 11.45 10.9 10.2 6.1 9.95 None
11 Feb 2026 None 132KV APO TS TR4- 100MVA 33KV FDR H33 132KV APO TS_33KV FDR H33_PL_PL AEDC L/S 19.55 17.4 16.5 16.9 18.85 19.6 16.25 15.35 14.8 14.5 11.6 14.8 12.7 15 15.9 INST.EF INST.EF INST.EF INST.EF INST.EF 18.65 16.5 INST. EF 11.6 16.1676470588235 None
11 Feb 2026 None 132KV APO TS TR4- 100MVA 33KV FDR H35 132KV APO TS_33KV FDR H35_PL_PL AEDC 7 6.25 6.05 5.85 5.75 6 5.8 4.85 4.8 4.7 6.65 6 7.15 7.2 7.15 7.6 7.55 INST. OC 2.1 2.2 2.3 2.2 2 2 2 5.1804347826087 None
11 Feb 2026 None 132KV APO TS TR4- 100MVA 33KV FDR H37 132KV APO TS_33KV FDR H37_PL_PL AEDC 6.85 6.2 5.85 5.55 5.45 5.6 5.45 4.6 4.45 4.4 4.45 4.4 4.4 4.6 4.4 4.3 2.25 5.05 2.9 2.95 3.35 3.25 5.85 7.4 2.25 4.74791666666667 None
11 Feb 2026 None 132KV APO TS TR2 45MVA 33KV FDR H5 132KV APO TS_33KV FDR H5_PL_PL AEDC 14.05 13.15 12.75 12.5 12.6 14.05 14.25 14.6 16.1 16.95 17.45 17.85 18.4 18.4 18.7 17.75 WP 15.6 16.65 13.05 12.9 12.6 12.1 15.1 12.1 15.1108695652174 None
11 Feb 2026 None 132KV APO TS TR2 45MVA 33KV FDR H7 132KV APO TS_33KV FDR H7_PL_PL AEDC 1.15 1.05 0.95 0.8 0.9 1.25 1.55 1.4 1.75 2.15 1.75 2.25 2.05 2.4 1.95 2.25 WP 0.35 2.05 1.55 1.45 1.8 1.5 1.35 0.35 1.55 None
11 Feb 2026 None 132KV KARU TS TR1- 100MVA 33KV FDR K1 132KV KARU TS_33KV FDR K1_PL_PL AEDC 13.5 12.5 12.3 12.2 13.4 14.1 10.9 11.2 5.5 5.3 5.3 5.3 5.7 9.3 11.8 12.8 12.8 13.6 15.3 13.7 14.4 LS/D LS/D LS/D 5.3 10.9952380952381 None
11 Feb 2026 None 132KV KARU TS TR1- 100MVA 33KV FDR K2 132KV KARU TS_33KV FDR K2_PL_PL AEDC LS/D LS/D LS/D LS/D LS/D 21.6 20.8 17.8 16 15.5 LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D 21.5 21.5 20 18.2 LS/D LS/D 15.5 19.2111111111111 None
11 Feb 2026 None 132KV KARU TS TR1- 100MVA 33KV FDR K3 132KV KARU TS_33KV FDR K3_PL_PL AEDC LS/D 6.5 6 5.9 LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D 7 7 7.2 7.3 LS/D LS/D LS/D LS/D LS/D LS/D 5.9 6.7 None
11 Feb 2026 None 132KV KARU TS TR2- 60MVA 33KV FDR K4 132KV KARU TS_33KV FDR K4_PL_PL AEDC LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D 13.6 16 15.5 8 11.2 12.2 LS/D LS/D LS/D LS/D LS/D LS/D 15.5 13.9 8 13.2375 None
11 Feb 2026 None 132KV KARU TS TR2- 60MVA 33KV FDR K5 132KV KARU TS_33KV FDR K5_PL_PL AEDC LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D 18.5 18.6 15 17 17.2 17.3 LS/D LS/D LS/D LS/D LS/D LS/D LS/D 14 18.1 16.5 14 16.9111111111111 None
11 Feb 2026 None 132KV KARU TS TR2- 60MVA 33KV FDR K6 132KV KARU TS_33KV FDR K6_PL_PL AEDC 9.1 8.5 8.2 8.2 8.7 LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D LS/D 10 10.1 10.3 10 LS/D LS/D LS/D LS/D LS/D LS/D 8.2 9.23333333333333 None
11 Feb 2026 None 132KV KUKWABA TS TR1- 60MVA 33KV FDR L31 132KV KUKWABA TS_33KV FDR L31_PL_PL AEDC 2.1 2.2 14 13.1 13 14.4 14.4 12.2 11.5 15.4 2.25 LS/T LS/T LS/T 15.9 15.5 10.8 11.5 12.7 13.7 O/C O/C O/C O/C 2.1 11.45 None
11 Feb 2026 None 132KV GWAGWALADA TS TR1-60MVA 33KV FDR L31 132KV KUKWABA TS_33KV FDR L31_PL_PL AEDC 16.98 11.36 10.85 14.79 15.46 11.84 12.38 10.5 10.7 10.4 11 10.7 10.6 15.9 16 16.4 11.7 E/F 7.1 13.4 13.1 13.4 18.3 16.6 7.1 13.02 None
11 Feb 2026 None 132KV KUKWABA TS TR1- 60MVA 33KV FDR L32 132KV GWAGWALADA TS_33KV FDR L32_PL_PL AEDC 13.6 14 12.3 15 15.6 15.2 15.1 12.6 11.9 10.8 10.9 11.3 11.2 LS/D LS/D 16.3 16.5 16.4 18.3 O/C O/C O/C O/C O/C 10.8 13.9411764705882 None
11 Feb 2026 None 132KV GWAGWALADA TS TR1-60MVA 33KV FDR L32 132KV GWAGWALADA TS_33KV FDR L32_PL_PL AEDC LS/D 10.14 9.87 9.94 11 13.4 13.99 12.2 11.4 9.6 9.6 10 10.1 10.4 I/S I/S I/S I/S 12.1 14.9 LS/D LS/D LS/D LS/D 9.6 11.2426666666667 None
« Previous Page 196 of 214 · 21338 readings Next »

Feeder names not matching MYTO

Feeder names on this page that do not correspond to a MYTO feeder name (NERC approved feeder name on the MYTO page). Select the correct MYTO feeder and confirm — the correction is shared by the availability, outage and hourly-load pages.

Source groupFeeder name (raw)Current MYTO feederSelect MYTO feederAction
Hourly Load 11KV CHANCHAGA FDR — —
Hourly Load 11KV DIKKO FDR — —
Hourly Load 11KV GAURAKA FDR — —
Hourly Load 11KV MINNA RD FDR — —
Hourly Load 11KV NNPC FDR — —
Hourly Load 11KV PARLFDR — —
Hourly Load 11KV SHIROROFDR — —
Hourly Load 11KV WATER WORKS FDR — —
Hourly Load 33KV AUCHI FDR — —
Hourly Load 33KV C1 FDR — —
Hourly Load 33KV C2 FDR — —
Hourly Load 33KV C3 FDR — —
Hourly Load 33KV C4 FDR — —
Hourly Load 33KV C5 FDR — —
Hourly Load 33KV C6 FDR — —
Hourly Load 33KV C7 FDR — —
Hourly Load 33KV C8 FDR — —
Hourly Load 33KV C9 FDR — —
Hourly Load 33KV CEMENT FACTORY FDR — —
Hourly Load 33KV CERAMICS FDR — —
Hourly Load 33KV FDR D3 — —
Hourly Load 33KV FDR D4 — —
Hourly Load 33KV FDR D5 — —
Hourly Load 33KV FDR GL33 — —
Hourly Load 33KV FDR GL36 — —
Hourly Load 33KV GANFENG-PENSTOCK FDR — —
Hourly Load 33KV GOODER TECH PLUS FDR — —
Hourly Load 33KV LUGBE FDR — —
Hourly Load 33KV OKPELLA TOWN FDR — —
Hourly Load ADOGO — —
Hourly Load AGWARA — —
Hourly Load ALIERO — —
Hourly Load ANYIGBA — —
Hourly Load ARGUNGU — —
Hourly Load ARMY BARRACK — —
Hourly Load ASCO 132KV — —
Hourly Load AUCHI — —
Hourly Load Al-Hassin Company — —
Hourly Load BIRIGIFDR — —
Hourly Load BUNZA — —
Hourly Load CCNN — —
Hourly Load CEMENT FACTORY — —
Hourly Load CERAMICS — —
Hourly Load CONFLUENCE — —
Hourly Load EVENT — —
Hourly Load Emergency — —
Hourly Load FADAMA 2 — —
Hourly Load FADAMA1 — —
Hourly Load FARFARU — —
Hourly Load FDR1 — —
Hourly Load FDR2 — —
Hourly Load FDR3 — —
Hourly Load FEEDER 1 — —
Hourly Load FEEDER 6 — —
Hourly Load Forced — —
Hourly Load GAYA — —
Hourly Load GRA 11kv fdr — —
Hourly Load GWANDU — —
Hourly Load HYDROPOLIS 1 — —
Hourly Load HYDROPOLIS 2 — —
Hourly Load I — —
Hourly Load I/S — —
Hourly Load J/Bachita — —
Hourly Load JEGA — —
Hourly Load KOKO — —
Hourly Load KWARE — —
Hourly Load LABANA — —
Hourly Load Life Camp — —
Hourly Load M/KUNKEL0DR — —
Hourly Load MASUGA FDR — —
Hourly Load Mokwa — —
Hourly Load NEW INJECTION — —
Hourly Load NGASKI — —
Hourly Load OKPELLA TOWN — —
Hourly Load P/ HOUSE — —
Hourly Load P/STATN — —
Hourly Load SPARE-II FDR — —
Hourly Load STEELPLANT — —
Hourly Load TAMBUWAL — —
Hourly Load Town 11KV fdr — —
Hourly Load UNIVERSITY — —
Hourly Load YABO — —
Hourly Load YAURI — —
Hourly Load ZURU — —