Date Region Substation Transformer (MVA) Feeder MYTO Feeder Disco 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Min Avg Max
14 Jul 2026 None 132KV CENTRAL AREA T/S TR1, TR2-2X60MVA 33KV C1 FDR — ABUJA - - - - - - - - - - - - - - - - - - - - - - - - None nan None
14 Jul 2026 None 132KV CENTRAL AREA T/S TR1, TR2-2X60MVA 33KV C2 FDR — ABUJA 3.2 2.6 1.8 3 2.8 3.4 3.8 4.2 4.8 4.5 4.9 5.3 5.4 6 4.9 5.7 4.8 0.8 INST. E/F INST. E/F 0.2 0.5 0.8 - None 3.3454545454545452 None
14 Jul 2026 None 132KV CENTRAL AREA T/S TR1, TR2-2X60MVA 33KV C3 FDR — ABUJA INST. O/C INST. O/C INST. O/C INST. O/C 1.2 3.8 4.9 5.6 11 13.2 12.9 13.2 11.8 4.7 3.1 E/F E/F E/F E/F E/F 5 5.4 6.3 - None 7.1933333333333325 None
14 Jul 2026 None 132KV CENTRAL AREA T/S TR1, TR2-2X60MVA 33KV C4 FDR — ABUJA 2.6 1.4 2.3 2.6 2.3 2.2 3.1 4.5 5.9 6.5 6.5 7 7.2 8.2 4 3.3 3.2 3 2.4 6.4 6.9 6.8 6.4 - None 4.6000000000000005 None
14 Jul 2026 None 132KV CENTRAL AREA T/S TR1, TR2-2X60MVA 33KV C5 FDR — ABUJA 5.4 5 4.9 5.5 4.6 4.3 5.5 7.9 9.8 10.7 11.1 12 12.1 14.5 2.9 INST. O/C 8 8.9 7.8 7.3 6.3 5.9 5.6 - None 7.456521739130436 None
14 Jul 2026 None 132KV CENTRAL AREA T/S TR1, TR2-2X60MVA 33KV C6 FDR — ABUJA 6.9 6.2 5.8 6.6 6.2 6.7 7.6 8.2 8.4 7.5 7.7 5.2 10.1 8.7 3.1 0.1 0.5 3.3 6 6.1 3 4 3.7 - None 5.633333333333332 None
14 Jul 2026 None 132KV CENTRAL AREA T/S TR3-60MVA 33KV C7 FDR — ABUJA - - - - - - - - - - - - - - - - - - - - - - - - None nan None
14 Jul 2026 None 132KV CENTRAL AREA T/S TR3-60MVA 33KV C8 FDR — ABUJA INST. O/C INST. O/C INST. O/C 3.7 10.5 9.9 10.5 11.1 12.1 16.1 14.6 18.5 4.8 8.9 11.1 15.6 14.8 2.1 O/C&E/F O/C&E/F 13 17.4 17 - None 11.978947368421053 None
14 Jul 2026 None 132KV CENTRAL AREA T/S TR3-60MVA 33KV C9 FDR — ABUJA - - - - - - - - - - - - - - - - - - - - - - - - None nan None
14 Jul 2026 None OKPELLA TS T1(15MVA)&T2(60MVA) 33KV CEMENT FACTORY FDR — BENIN CB/F CB/F CB/F CB/F CB/F CB/F CB/F CB/F CB/F CB/F CB/F CB/F CB/F CB/F CB/F CB/F CB/F CB/F CB/F CB/F CB/F CB/F CB/F - None nan None
14 Jul 2026 None 132KVAJAOKUTA TS T1- 30MVA 33KV CERAMICS FDR — ABUJA 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.3 0.4 0.4 0.3 0.4 0.4 0.4 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 - None 0.1791666666666666 None
14 Jul 2026 None 132KVAJAOKUTA TS T2- 60MVA 33KV CONFLUENCE FDR 132KV AJAOKUTA TS_33KV CONFLUENCE FDR_PL_PL ABUJA E/F 5.5 5.7 5.9 7.5 7.4 8.5 7.1 6.6 6 5.9 6 6.3 7 7.1 7.3 7.5 7.7 8.5 9.4 8.8 7.8 7 - None 7.069565217391306 None
14 Jul 2026 None 132KV KUBWA TS TR1- 60MVA 33KV DAM FDR 132KV KUBWA TS_33KV DAM FDR_PL_PL AEDC 0.6 0.5 0.5 0.5 0.6 0.6 0.8 0.6 0.7 0.4 0.4 0.5 0.5 0.5 0.5 0.7 0.6 0.7 0.7 0.8 0.7 0.6 0.6 0.5 0.4 0.5875 None
14 Jul 2026 None 132KV KUBWA T/S TR1- 60MVA 33KV DAM FDR 132KV KUBWA TS_33KV DAM FDR_PL_PL ABUJA 0.6 0.5 0.5 0.5 0.6 0.6 0.8 0.6 0.7 0.4 0.4 0.5 0.5 0.5 0.5 0.7 0.6 0.7 0.7 0.8 0.7 0.6 0.6 - None 0.5874999999999999 None
14 Jul 2026 None 132KV KUBWA TS TR1- 60MVA 33KV DAWAKI FDR 132KV KUBWA TS_33KV DAWAKI FDR_PL_PL AEDC 9.3 E/F 15.4 7.5 7.9 9 9.2 8.1 7.3 5.6 5.1 4.95 6.5 6.6 7 E/F E/F 10.3 8.7 9.6 11.8 10.8 10.2 9 4.95 8.564285714 None
14 Jul 2026 None 132KV KUBWA T/S TR1- 60MVA 33KV DAWAKI FDR 132KV KUBWA TS_33KV DAWAKI FDR_PL_PL ABUJA 9.3 E/F 15.4 7.5 7.9 9 9.2 8.1 7.3 5.6 5.1 5 6.5 6.6 7 E/F E/F 10.3 8.7 9.6 11.8 10.8 10.2 - None 8.566666666666666 None
14 Jul 2026 None 132KV KUBWA TS TR1- 60MVA 33KV DEIDEI FDR 132KV KUBWA TS_33KV DEIDEI FDR_PL_PL AEDC 11.8 8.3 7.9 9.4 10.6 12.8 13.6 13.4 12.9 12.2 12 11.65 10.9 11.1 10.9 INST/OC INST/OC 12.5 12.9 15.2 14.9 16.2 13.6 12.6 7.9 12.15227273 None
14 Jul 2026 None 132KV KUBWA T/S TR1- 60MVA 33KV DEIDEI FDR 132KV KUBWA TS_33KV DEIDEI FDR_PL_PL ABUJA 11.8 8.3 7.9 9.4 10.6 12.8 13.6 13.4 12.9 12.2 12 11.7 10.9 11.1 10.9 INST.O/C INST.O/C 12.5 12.9 15.2 14.9 16.2 13.6 - None 12.154545454545454 None
14 Jul 2026 None 132KV LAFIA TS TR1- 60MVA 33KV FDR A1 33OKV APIR-LAFIA LINE 1&2_132KV LAFIA TS_33KV 33KV FDR A1_PL_PL AEDC 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 None
14 Jul 2026 None 132KV LAFIA TS TR1- 60MVA 33KV FDR A2 33OKV APIR-LAFIA LINE 1&2_132KV LAFIA TS_33KV 33KV FDR A2_PL_PL AEDC 8.6 7.6 7.2 7.4 8.1 6.3 8.7 11.5 11.7 8.7 8.6 8.5 8.1 11.6 9.8 3.1 2.4 7.6 9.1 10 12.6 E/F 17.8 15.3 2.4 9.143478261 None
14 Jul 2026 None 132KV LAFIA TS TR2- 60MVA 33KV FDR A5 33OKV APIR-LAFIA LINE 1&2_132KV LAFIA TS_33KV FDR A5_PL_PL AEDC 0.6 0.6 0.6 0.6 0.6 0.7 0.8 0.8 0.8 4.7 6.3 6.1 6.1 6.3 7.3 7.7 7.9 8.1 8.8 8.7 7.5 7 6 5.4 0.6 4.583333333 None
14 Jul 2026 None 132KV CENTRAL AREA TS TR1 - 100MVA 33KV FDR 1 132KV CENTRAL AREA TS_33KV FDR 1_PL_PL AEDC - - - - - - - - - - - - - - - - - - - - - - - - 0 #DIV/0! None
14 Jul 2026 None LOKOJA TS T1(60MVA) 33KV FDR 1 132KV CENTRAL AREA TS_33KV FDR 1_PL_PL ABUJA 1.5 1.5 1.5 1.5 1.6 1.9 3.7 3.2 3 O/C&E/F O/C&E/F O/C&E/F O/C&E/F O/C&E/F 1.9 2 2 2 2.2 2.7 2.5 3.8 3.3 - None 2.378947368421052 None
14 Jul 2026 None 132KV CENTRAL AREA TS TR1 - 100MVA 33KV FDR 2 132KV CENTRAL AREA TS_33KV FDR 2_PL_PL AEDC 3.2 2.59 1.84 2.97 2.81 3.36 3.78 4.21 4.81 4.5 4.88 5.33 5.41 6 4.88 5.72 4.82 0.81 INST. E/F INST. E/F 0.15 0.52 0.84 0.24 0.15 3.348636364 None
14 Jul 2026 None LOKOJA TS T1(60MVA) 33KV FDR 2 132KV CENTRAL AREA TS_33KV FDR 2_PL_PL ABUJA 17.1 17 16.4 17.3 19.6 24.2 24.9 21 20.1 O/C&E/F O/C&E/F O/C&E/F 21.2 21 23.2 23.7 16.9 18.5 24.8 18.1 17 12.9 11.9 - None 19.29523809523809 None
14 Jul 2026 None 132KV CENTRAL AREA TS TR1 - 100MVA 33KV FDR 3 132KV CENTRAL AREA TS_33KV FDR 3_PL_PL AEDC INST. O/C INST. O/C INST. O/C INST. O/C 1.17 3.78 4.88 5.57 10.97 13.16 12.88 13.2 11.82 4.74 3.13 E/F E/F E/F E/F E/F 5.02 5.4 6.32 5.76 1.17 7.186666667 None
14 Jul 2026 None LOKOJA TS T1(60MVA) 33KV FDR 3 132KV CENTRAL AREA TS_33KV FDR 3_PL_PL ABUJA 3 2.9 2.8 2.8 2.8 3.2 3.1 2.2 3.7 4.1 4.2 4.3 4.3 4.2 4.3 4.1 3.8 3.6 3.7 4.1 4.1 3.8 3.4 - None 3.570833333333333 None
14 Jul 2026 None 132KV CENTRAL AREA TS TR1 - 100MVA 33KV FDR 4 132KV CENTRAL AREA TS_33KV FDR 4_PL_PL AEDC 2.64 1.41 2.32 2.57 2.25 2.23 3.06 4.47 5.85 6.51 6.45 7 7.16 8.16 3.98 3.27 3.15 3.01 2.39 6.43 6.89 6.79 6.41 5.74 1.41 4.589166667 None
14 Jul 2026 None 132KV CENTRAL AREA TS TR2- 100MVA 33KV FDR 5 132KV CENTRAL AREA TS_33KV FDR 5_PL_PL AEDC 5.37 5.04 4.93 5.45 4.58 4.28 5.51 7.85 9.79 10.69 11.09 12 12.09 14.5 2.9 INST. O/C 7.98 8.9 7.83 7.31 6.29 5.87 5.61 5.52 2.9 7.451304348 None
14 Jul 2026 None 132KV CENTRAL AREA TS TR2- 100MVA 33KV FDR 6 132KV CENTRAL AREA TS_33KV FDR 6_PL_PL AEDC 6.92 6.16 5.77 6.59 6.18 6.67 7.64 8.17 8.36 7.46 7.74 5.22 10.13 8.73 3.06 0.08 0.45 3.34 6.03 6.12 2.96 4.01 3.73 3.6 0.08 5.63 None
14 Jul 2026 None 132KV CENTRAL AREA TS TR3-60MVA 33KV FDR 7 132KV CENTRAL AREA TS_33KV FDR 7_PL_PL AEDC - - - - - - - - - - - - - - - - - - - - - - - - 0 #DIV/0! None
14 Jul 2026 None 132KV CENTRAL AREA TS TR3-60MVA 33KV FDR 8 132KV CENTRAL AREA TS_33KV FDR 8_PL_PL AEDC INST. O/C INST. O/C INST. O/C 3.68 10.54 9.85 10.53 11.09 12.11 16.11 14.62 18.53 4.83 8.93 11.09 15.57 14.81 2.07 O/C&E/F O/C&E/F 12.98 17.44 16.96 15.87 2.07 11.97947368 None
14 Jul 2026 None 132KV CENTRAL AREA TS TR3-60MVA 33KV FDR 9 132KV CENTRAL AREA TS_33KV FDR 9_PL_PL AEDC - - - - - - - - - - - - - - - - - - - - - - - - 0 #DIV/0! None
14 Jul 2026 None 132KV LAFIA T/S TR1- 60MVA 33KV FDR A1 33OKV APIR-LAFIA LINE 1&2_132KV LAFIA TS_33KV 33KV FDR A1_PL_PL ABUJA 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 0.6 - None 0.5999999999999998 None
14 Jul 2026 None 132KV LAFIA T/S TR1- 60MVA 33KV FDR A2 33OKV APIR-LAFIA LINE 1&2_132KV LAFIA TS_33KV 33KV FDR A2_PL_PL ABUJA 8.6 7.6 7.2 7.4 8.1 6.3 8.7 11.5 11.7 8.7 8.6 8.5 8.1 11.6 9.8 3.1 2.4 7.6 9.1 10 12.6 E/F 17.8 - None 9.143478260869564 None
14 Jul 2026 None 132KV LAFIA T/S TR2- 60MVA 33KV FDR A5 33OKV APIR-LAFIA LINE 1&2_132KV LAFIA TS_33KV FDR A5_PL_PL ABUJA 0.6 0.6 0.6 0.6 0.6 0.7 0.8 0.8 0.8 4.7 6.3 6.1 6.1 6.3 7.3 7.7 7.9 8.1 8.8 8.7 7.5 7 6 - None 4.583333333333333 None
14 Jul 2026 None 132KV DAWAKI TS TR1 - 60MVA 33KV FDR D1 132KV GIS DAWAKI TS_33KV FDR D1_PL_PL AEDC 8.1 7.4 6.9 6.8 7.3 8.7 9.6 8.5 8.2 7.9 7.3 7.5 7.4 7.7 8 8.2 5.9 6.2 7 8.2 8.2 8.1 7.5 6.9 5.9 7.645833333 None
14 Jul 2026 None 132KV DAWAKI T/S TR1- 60MVA 33KV FDR D1 132KV GIS DAWAKI TS_33KV FDR D1_PL_PL ABUJA 8.1 7.4 6.9 6.8 7.3 8.7 9.6 8.5 8.2 7.9 7.3 7.5 7.4 7.7 8 8.2 5.9 6.2 7 8.2 8.2 8.1 7.5 - None 7.645833333333332 None
14 Jul 2026 None 132KV DAWAKI TS TR1 - 60MVA 33KV FDR D2 132KV GIS DAWAKI TS_33KV FDR D2_PL_PL AEDC 11.5 10.4 9.7 9.5 9.9 10.7 11.4 11 10.9 11.5 11.4 11.1 11.4 11.9 11.9 11.1 9.5 11.9 13.1 14.4 14.4 13.9 13.1 12.1 9.5 11.57083333 None
14 Jul 2026 None 132KV DAWAKI T/S TR1- 60MVA 33KV FDR D2 132KV GIS DAWAKI TS_33KV FDR D2_PL_PL ABUJA 11.5 10.4 9.7 9.5 9.9 10.7 11.4 11 10.9 11.5 11.4 11.1 11.4 11.9 11.9 11.1 9.5 11.9 13.1 14.4 14.4 13.9 13.1 - None 11.570833333333335 None
14 Jul 2026 None 132KV DAWAKI TS TR1 - 60MVA 33KV FDR D3 — AEDC - - - - - - - - - - - - - - - - - - - - - - - - 0 #DIV/0! None
14 Jul 2026 None 132KV DAWAKI T/S TR1- 60MVA 33KV FDR D3 — ABUJA SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE - None nan None
14 Jul 2026 None 132KV DAWAKI TS TR2- 60MVA 33KV FDR D4 — AEDC - - - - - - - - - - - - - - - - - - - - - - - - 0 #DIV/0! None
14 Jul 2026 None 132KV DAWAKI T/S TR2- 60MVA 33KV FDR D4 — ABUJA SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE SPARE - None nan None
14 Jul 2026 None 132KV DAWAKI TS TR2- 60MVA 33KV FDR D5 — AEDC I/S I/S I/S I/S I/S I/S I/S I/S 0.75 0.57 0.58 0.39 0.35 0.91 0.74 0.56 I/S I/S I/S I/S I/S I/S I/S I/S 0.35 0.60625 None
14 Jul 2026 None 132KV DAWAKI T/S TR2- 60MVA 33KV FDR D5 — ABUJA I/S I/S I/S I/S I/S I/S I/S I/S 0.8 0.6 0.6 0.4 0.4 0.9 0.7 0.6 I/S I/S I/S I/S I/S I/S I/S - None 0.6249999999999999 None
14 Jul 2026 None 132KV DAWAKI TS TR2- 60MVA 33KV FDR D6 132KV GIS DAWAKI TS_33KV FDR D6_PL_PL AEDC 1.01 0.92 0.88 0.85 0.84 0.96 0.99 0.89 0.83 0.83 0.77 0.74 0.73 0.79 0.76 0.74 0.76 0.81 0.93 1.13 1.22 1.2 1.11 1.02 0.73 0.9045833333 None
14 Jul 2026 None 132KV DAWAKI T/S TR2- 60MVA 33KV FDR D6 132KV GIS DAWAKI TS_33KV FDR D6_PL_PL ABUJA 1 0.9 0.9 0.9 0.8 1 1 0.9 0.8 0.8 0.8 0.7 0.7 0.8 0.8 0.7 0.8 0.8 0.9 1.1 1.2 1.2 1.1 - None 0.9000000000000002 None
14 Jul 2026 None 330KV GWAGWALADA T/S TR1-60MVA 33KV FDR GL31 132KV GWAGWALADA TS_33KV FDR L31_PL_PL ABUJA 12.2 11.7 E/F E/F E/F E/F 15.1 16.5 14.3 14.2 17.1 16.2 16.4 12.4 12.8 4.8 5.1 8.4 9.8 11.8 13.9 16.9 14.5 - None 12.860000000000003 None
14 Jul 2026 None 330KV GWAGWALADA T/S TR1-60MVA 33KV FDR GL32 132KV GWAGWALADA TS_33KV FDR L32_PL_PL ABUJA 6.4 E/F E/F E/F E/F E/F E/F E/F E/F E/F E/F E/F 1.2 1.4 1.5 1.6 O/C O/C O/C 9.2 12.2 10.8 10.5 - None 6.26 None
14 Jul 2026 None 330KV GWAGWALADA T/S TR1-60MVA 33KV FDR GL33 — ABUJA - - - - - - - - - - - - - - - - - - - - - - - - None nan None
14 Jul 2026 None 330KV GWAGWALADA T/S TR2-60MVA 33KV FDR GL34 132KV GWAGWALADA TS_33KV FDR L34_PL_PL ABUJA 5.8 E/F&O/C E/F&O/C E/F&O/C E/F&O/C E/F&O/C 2.3 2.3 10.7 10.2 14.7 14.5 14.5 14.6 15.1 15.2 10.4 2.3 2.5 7.7 7.5 9.8 13.9 - None 9.799999999999999 None
14 Jul 2026 None 330KV GWAGWALADA T/S TR2-60MVA 33KV FDR GL35 132KV GWAGWALADA TS_33KV FDR L35_PL_PL ABUJA E/F E/F E/F E/F E/F E/F E/F E/F E/F E/F E/F E/F E/F E/F E/F E/F E/F E/F E/F E/F E/F E/F E/F - None nan None
14 Jul 2026 None 330KV GWAGWALADA T/S TR2-60MVA 33KV FDR GL36 — ABUJA - - - - - - - - - - - - - - - - - - - - - - - - None nan None
14 Jul 2026 None 132KV APO TS TR3- 100MVA 33KV FDR H1 132KV APO TS_33KV FDR H1_PL_PL AEDC 6.9 5.95 5.8 5.9 6.25 7.55 8.55 9.75 11.2 11.65 10.2 EMG EMG 6.7 6.05 5.55 4.55 4.15 3.75 9 8 8.25 7.75 7.2 3.75 7.302272727 None
14 Jul 2026 None 132KV APO T/S TR3- 100MVA 33KV FDR H1 132KV APO TS_33KV FDR H1_PL_PL ABUJA 6.9 6 5.8 5.9 6.3 7.6 8.6 9.8 11.2 11.7 10.2 E E 6.7 6.1 5.6 4.6 4.2 3.8 9 8 8.3 7.8 - None 7.331818181818182 None
14 Jul 2026 None 132KV APO TS TR1 60MVA 33KV FDR H11 132KV APO TS_33KV FDR H11_PL_PL AEDC 0.9 0.9 0.9 2.7 2.6 2.7 2.7 3.0 3.3 3.4 3.5 3.5 4.8 5.0 4.9 4.7 3.6 1.1 3.2 3.0 5.0 4.4 - - None None None
14 Jul 2026 None 132KV APO TS TR1 60MVA 33KV FDR H11 132KV APO TS_33KV FDR H11_PL_PL AEDC 3.75 1 0.9 3.55 2.45 2.7 3.2 3.8 5.9 6.8 6.8 6.85 7 6.95 5.3 5.4 4.85 3.7 4.2 4.2 4.5 4.15 3.85 3.7 0.9 4.395833333 None
14 Jul 2026 None 132KV APO T/S TR1 45MVA 33KV FDR H11 132KV APO TS_33KV FDR H11_PL_PL ABUJA 3.8 1 0.9 3.6 2.5 2.7 3.2 3.8 5.9 6.8 6.8 6.9 7 7 5.3 5.4 4.9 3.7 4.2 4.2 4.5 4.2 3.9 - None 4.4125000000000005 None
14 Jul 2026 None 132KV APO TS TR1 60MVA 33KV FDR H13 132KV APO TS_33KV FDR H13 (JICA)_PL_PL AEDC I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S 0 #DIV/0! None
14 Jul 2026 None 132KV APO T/S TR1 45MVA 33KV FDR H13 132KV APO TS_33KV FDR H13 (JICA)_PL_PL ABUJA I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S I/S - None nan None
14 Jul 2026 None 132KV APO TS TR1 60MVA 33KV FDR H15 132KV APO TS_33KV FDR H15_PL_PL AEDC 0.75 0.7 0.7 0.7 0.7 0.9 1 1.15 0.8 1.7 1.35 1.95 1.9 1.95 1.35 0.85 1.1 0.9 0.9 1 0.6 0.7 0.8 0.8 0.6 1.052083333 None
14 Jul 2026 None 132KV APO T/S TR1 45MVA 33KV FDR H15 132KV APO TS_33KV FDR H15_PL_PL ABUJA 0.8 0.7 0.7 0.7 0.7 0.9 1 1.2 0.8 1.7 1.4 2 1.9 2 1.4 0.9 1.1 0.9 0.9 1 0.6 0.7 0.8 - None 1.0666666666666667 None
14 Jul 2026 None 132KV APO TS TR3- 100MVA 33KV FDR H2 132KV APO TS_33KV FDR H2_PL_PL AEDC 3.2 1 0.95 1 0.65 4.15 3.8 4.15 4.55 4.7 4.55 4.6 5.05 5 3.8 4.05 3.9 3.7 3.2 2.8 3 2.9 2.8 2.6 0.65 3.3375 None
14 Jul 2026 None 132KV APO T/S TR3- 100MVA 33KV FDR H2 132KV APO TS_33KV FDR H2_PL_PL ABUJA 3.2 1 1 1 0.7 4.2 3.8 4.2 4.6 4.7 4.6 4.6 5.1 5 3.8 4.1 3.9 3.7 3.2 2.8 3 2.9 2.8 - None 3.3541666666666665 None
14 Jul 2026 None 132KV APO TS TR3- 100MVA 33KV FDR H21 132KV APO TS_33KV FDR H21_PL_PL AEDC 8.6 INST EF INST EF INST EF 10.2 14.2 6.7 11.25 10.4 10 10 9 10.5 12 12.3 11.6 7.55 13 13 13.8 13.1 11.55 13.4 13.05 6.7 11.2 None
14 Jul 2026 None 132KV APO T/S TR3- 100MVA 33KV FDR H21 132KV APO TS_33KV FDR H21_PL_PL ABUJA 8.6 INST. E/F INST. E/F INST. E/F 10.2 14.2 6.7 11.3 10.4 10 10 9 10.5 12 12.3 11.6 7.6 13 13 13.8 13.1 11.6 13.4 - None 11.20952380952381 None
14 Jul 2026 None 132KV APO TS TR3- 100MVA 33KV FDR H23 132KV APO TS_33KV FDR H23_PL_PL AEDC 7.4 7 7.2 INST EF INST EF INST EF 8.2 8.6 12 12.2 13 12.8 13 13.6 13.2 INST EF 10.4 7.2 7.2 7.6 7.4 6.8 6.6 6.2 6.2 9.38 None
14 Jul 2026 None 132KV APO T/S TR3- 100MVA 33KV FDR H23 132KV APO TS_33KV FDR H23_PL_PL ABUJA 7.4 7 7.2 INST. E/F INST. E/F INST. E/F 8.2 8.6 12 12.2 13 12.8 13 13.6 13.2 INST. E/F 10.4 7.2 7.2 7.6 7.4 6.8 6.6 - None 9.379999999999999 None
14 Jul 2026 None 132KV APO TS TR3- 100MVA 33KV FDR H3 132KV APO TS_33KV FDR H3_PL_PL AEDC 9.8 9.4 9.15 9.05 9.3 13.3 11.6 12.7 13.55 13.4 13.65 13.85 14.35 14.05 8.95 INST EF 8 9.5 12.85 13.4 9.8 9.1 8.7 8.1 8 11.11086957 None
14 Jul 2026 None 132KV APO T/S TR3- 100MVA 33KV FDR H3 132KV APO TS_33KV FDR H3_PL_PL ABUJA 9.8 9.4 9.2 9.1 9.3 13.3 11.6 12.7 13.6 13.4 13.7 13.9 14.4 14.1 9 INST. E/F 8 9.5 12.9 13.4 9.8 9.1 8.7 - None 11.130434782608695 None
14 Jul 2026 None 132KV APO TS TR4- 100MVA 33KV FDR H31 132KV APO TS_33KV FDR H31_PL_PL AEDC 10 8.6 7.8 7.5 7.75 9.2 10 9.6 9.55 INST OC INST OC INST OC 13.85 13.8 INST EF INST EF 9.35 8.8 13.4 9.3 9.3 14.65 13.5 11.9 7.5 10.41315789 None
14 Jul 2026 None 132KV APO T/S TR4- 100MVA 33KV FDR H31 132KV APO TS_33KV FDR H31_PL_PL ABUJA 10 8.6 7.8 7.5 7.8 9.2 10 9.6 9.6 INST. O/C INST. O/C INST. O/C 13.9 13.8 INST. E/F INST. E/F 9.4 8.8 13.4 9.3 9.3 14.7 13.5 - None 10.426315789473685 None
14 Jul 2026 None 132KV APO TS TR4- 100MVA 33KV FDR H33 132KV APO TS_33KV FDR H33_PL_PL AEDC 13.3 INST EF INST EF INST EF INST EF INST EF INST EF INST EF INST EF INST EF 14.9 13.85 12.2 12.9 12.45 2.3 13 17.7 14.2 20.5 19.15 17.9 15.6 13.8 2.3 14.25 None
14 Jul 2026 None 132KV APO T/S TR4- 100MVA 33KV FDR H33 132KV APO TS_33KV FDR H33_PL_PL ABUJA 13.3 INST. E/F INST EF INST EF INST EF INST EF INST EF INST EF INST EF INST EF 14.9 13.9 12.2 12.9 12.5 2.3 13 17.7 14.2 20.5 19.2 17.9 15.6 - None 14.26 None
14 Jul 2026 None 132KV APO TS TR4- 100MVA 33KV FDR H35 132KV APO TS_33KV FDR H35_PL_PL AEDC 6.45 6.4 5.25 5 5.4 6.6 7.25 6.6 6 5.55 5.5 5.4 5.6 4.05 4.05 2.3 2.1 6.35 8 8.4 8.2 7.8 7.05 6.2 2.1 5.895833333 None
14 Jul 2026 None 132KV APO T/S TR4- 100MVA 33KV FDR H35 132KV APO TS_33KV FDR H35_PL_PL ABUJA 6.5 6.4 5.3 5 5.4 6.6 7.3 6.6 6 5.6 5.5 5.4 5.6 4.1 4.1 2.3 2.1 6.4 8 8.4 8.2 7.8 7.1 - None 5.912499999999999 None
14 Jul 2026 None 132KV APO TS TR4- 100MVA 33KV FDR H37 132KV APO TS_33KV FDR H37_PL_PL AEDC 4.6 4.2 3.7 3.6 3.7 4 4.15 3.8 3.6 3.5 3.3 3.2 3.3 3.35 3.5 3.6 3.4 3.65 4.3 4.8 5 4.85 4.65 4.3 3.2 3.91875 None
14 Jul 2026 None 132KV APO T/S TR4- 100MVA 33KV FDR H37 132KV APO TS_33KV FDR H37_PL_PL ABUJA 4.6 4.2 3.7 3.6 3.7 4 4.2 3.8 3.6 3.5 3.3 3.2 3.3 3.4 3.5 3.6 3.4 3.7 4.3 4.8 5 4.9 4.7 - None 3.9291666666666667 None
14 Jul 2026 None 132KV APO TS TR2 45MVA 33KV FDR H5 132KV APO TS_33KV FDR H5_PL_PL AEDC 9.6 9.3 8.45 8.35 8.7 10.25 14.2 14.85 15.3 15.3 12.25 12.3 12.45 12.55 8.55 5.85 8.35 8.1 8.75 11.3 10.7 10.15 12.55 12.15 5.85 10.84583333 None
14 Jul 2026 None 132KV APO T/S TR2 45MVA 33KV FDR H5 132KV APO TS_33KV FDR H5_PL_PL ABUJA 9.6 9.3 8.5 8.4 8.7 10.3 14.2 14.9 15.3 15.3 12.3 12.3 12.5 12.6 8.6 5.9 8.4 8.1 8.8 11.3 10.7 10.2 12.6 - None 10.875 None
14 Jul 2026 None 132KV APO TS TR2 45MVA 33KV FDR H7 132KV APO TS_33KV FDR H7_PL_PL AEDC 0.045 0.9 1.55 1.35 1.6 1.25 1.5 1.6 2 1.8 2.05 1.3 2.05 2 0.85 INST.OC/EF 0.8 2.05 0.03 1.3 1.3 1.5 1.65 1.4 0.03 1.385869565 None
14 Jul 2026 None 132KV APO T/S TR2 45MVA 33KV FDR H7 132KV APO TS_33KV FDR H7_PL_PL ABUJA 0 0.9 1.6 1.4 1.6 1.3 1.5 1.6 2 1.8 2.1 1.3 2.1 2 0.9 INST.O/C&E/F 0.8 2.1 0 1.3 1.3 1.5 1.7 - None 1.4000000000000001 None
14 Jul 2026 None 132KV KARU TS TR1- 100MVA 33KV FDR K1 132KV KARU TS_33KV FDR K1_PL_PL AEDC 9.1 8.2 8.1 8 8.7 10.3 10.9 9.8 9.5 9.4 8.9 9 9.3 6.6 10.6 10.2 10 10.6 12 14.1 13.7 11.7 10.9 9.5 6.6 9.9625 None
14 Jul 2026 None 132KV KARU T/S TR1- 60MVA 33KV FDR K1 132KV KARU TS_33KV FDR K1_PL_PL ABUJA 9.1 8.2 8.1 8 8.7 10.3 10.9 9.8 9.5 9.4 8.9 9 9.3 6.6 10.6 10.2 10 10.6 12 14.1 13.7 11.7 10.9 - None 9.962499999999999 None
14 Jul 2026 None 132KV KARU TS TR1- 100MVA 33KV FDR K2 132KV KARU TS_33KV FDR K2_PL_PL AEDC 13.1 10 9.4 9.2 10.3 12.8 14.2 12.8 12.9 12.3 11.8 11.5 11.5 11.9 11.3 11.1 12.7 LS/D LS/D LS/D 18.3 14.6 13.5 11.4 9.2 12.21904762 None
14 Jul 2026 None 132KV KARU T/S TR1- 60MVA 33KV FDR K2 132KV KARU TS_33KV FDR K2_PL_PL ABUJA 13.1 10 9.4 9.2 10.3 12.8 14.2 12.8 12.9 12.3 11.8 11.5 11.5 11.9 11.3 11.1 12.7 LS/D LS/D LS/D 18.3 14.6 13.5 - None 12.21904761904762 None
14 Jul 2026 None 132KV KARU TS TR1- 100MVA 33KV FDR K3 132KV KARU TS_33KV FDR K3_PL_PL AEDC 4.4 3.9 3.6 3.7 4.2 5 5.2 4.4 4.1 4 3.8 3.8 4 4.2 4.4 4.5 4.2 5 5.5 6 LS/D LS/D 5.8 4.3 3.6 4.454545455 None
14 Jul 2026 None 132KV KARU T/S TR1- 60MVA 33KV FDR K3 132KV KARU TS_33KV FDR K3_PL_PL ABUJA 4.4 3.9 3.6 3.7 4.2 5 5.2 4.4 4.1 4 3.8 3.8 4 4.2 4.4 4.5 4.2 5 5.5 6 LS/D LS/D 5.8 - None 4.454545454545454 None
14 Jul 2026 None 132KV KARU TS TR2- 60MVA 33KV FDR K4 132KV KARU TS_33KV FDR K4_PL_PL AEDC 9.5 INST OC INST OC INST OC INST OC 1.3 INST OC INST OC INST OC INST OC INST OC INST OC SG SG SG SG SG 15.2 14.7 14.1 7 9.1 8.1 8.9 1.3 9.766666667 None
14 Jul 2026 None 132KV KARU T/S TR2- 60MVA 33KV FDR K4 132KV KARU TS_33KV FDR K4_PL_PL ABUJA 9.5 INST. O/C INST. O/C INST. O/C INST. O/C 1.3 INST. O/C INST. O/C INST. O/C INST. O/C INST. O/C INST. O/C SG SG SG SG SG 15.2 14.7 14.1 7 9.1 8.1 - None 9.766666666666667 None
14 Jul 2026 None 132KV KARU TS TR2- 60MVA 33KV FDR K5 132KV KARU TS_33KV FDR K5_PL_PL AEDC E/F 8 7.8 8.1 9.5 12 13.2 12.2 11.3 11.6 10.2 10 10.1 10.7 11.5 11.5 SWS 12.1 12.6 LS/D LS/D LS/D LS/D LS/D 7.8 10.72941176 None
14 Jul 2026 None 132KV KARU T/S TR2- 60MVA 33KV FDR K5 132KV KARU TS_33KV FDR K5_PL_PL ABUJA E/F 8 7.8 8.1 9.5 12 13.2 12.2 11.3 11.6 10.2 10 10.1 10.7 11.5 11.5 SWS 12.1 12.6 LS/D LS/D LS/D LS/D - None 10.729411764705882 None
14 Jul 2026 None 132KV KARU TS TR2- 60MVA 33KV FDR K6 132KV KARU TS_33KV FDR K6_PL_PL AEDC 5.1 E/F 5.4 5.1 5.9 7.4 7.5 6.6 7.6 6.1 5.9 6 6.3 6 6.7 6.9 6.7 6.8 7.8 8.5 LS/D LS/D 8.1 6.2 5.1 6.6 None
14 Jul 2026 None 132KV KARU T/S TR2- 60MVA 33KV FDR K6 132KV KARU TS_33KV FDR K6_PL_PL ABUJA 5.1 E/F 5.4 5.1 5.9 7.4 7.5 6.6 7.6 6.1 5.9 6 6.3 6 6.7 6.9 6.7 6.8 7.8 8.5 LS/D LS/D 8.1 - None 6.6 None
14 Jul 2026 None 132KV KUKWABA TS TR1- 60MVA 33KV FDR L31 132KV KUKWABA TS_33KV FDR L31_PL_PL AEDC 12.2 10.4 10.2 10 14.4 12 12.9 11.7 14.5 10.8 10.7 10.6 10.8 11 11.7 11.5 INST. E/F INST. E/F INST. E/F INST. E/F 2.8 2.4 18.1 13.2 2.4 11.095 None
14 Jul 2026 None 132KV GWAGWALADA TS TR1-60MVA 33KV FDR L31 132KV KUKWABA TS_33KV FDR L31_PL_PL AEDC 12.2 11.7 E/F E/F E/F E/F 15.1 16.5 14.3 14.2 17.1 16.2 16.4 12.4 12.8 4.8 5.1 8.4 9.8 11.8 13.9 16.9 14.5 13.1 4.8 12.86 None
14 Jul 2026 None 132KV KUKWABA T/S TR1- 60MVA 33KV FDR L31 132KV KUKWABA TS_33KV FDR L31_PL_PL ABUJA 12.2 10.4 10.2 10 14.4 12 12.9 11.7 14.5 10.8 10.7 10.6 10.8 11 11.7 11.5 INST. E/F INST. E/F INST. E/F INST. E/F 2.8 2.4 18.1 - None 11.094999999999999 None
14 Jul 2026 None 132KV KUKWABA TS TR1- 60MVA 33KV FDR L32 132KV GWAGWALADA TS_33KV FDR L32_PL_PL AEDC INST E/F INST E/F INST E/F INST E/F INST E/F INST E/F INST E/F INST E/F INST E/F INST E/F 14.1 11.3 11.6 11.2 LSD LSD 17.7 15 13.6 13.8 13 11.6 LS/T LS/T 11.2 13.29 None
14 Jul 2026 None 132KV GWAGWALADA TS TR1-60MVA 33KV FDR L32 132KV GWAGWALADA TS_33KV FDR L32_PL_PL AEDC 6.4 E/F E/F E/F E/F E/F E/F E/F E/F E/F E/F E/F 1.2 1.4 1.5 1.6 O/C O/C O/C 9.2 12.2 10.8 10.5 7.8 1.2 6.26 None
« Previous Page 20 of 214 · 21338 readings Next »

Feeder names not matching MYTO

Feeder names on this page that do not correspond to a MYTO feeder name (NERC approved feeder name on the MYTO page). Select the correct MYTO feeder and confirm — the correction is shared by the availability, outage and hourly-load pages.

Source groupFeeder name (raw)Current MYTO feederSelect MYTO feederAction
Hourly Load 11KV CHANCHAGA FDR — —
Hourly Load 11KV DIKKO FDR — —
Hourly Load 11KV GAURAKA FDR — —
Hourly Load 11KV MINNA RD FDR — —
Hourly Load 11KV NNPC FDR — —
Hourly Load 11KV PARLFDR — —
Hourly Load 11KV SHIROROFDR — —
Hourly Load 11KV WATER WORKS FDR — —
Hourly Load 33KV AUCHI FDR — —
Hourly Load 33KV C1 FDR — —
Hourly Load 33KV C2 FDR — —
Hourly Load 33KV C3 FDR — —
Hourly Load 33KV C4 FDR — —
Hourly Load 33KV C5 FDR — —
Hourly Load 33KV C6 FDR — —
Hourly Load 33KV C7 FDR — —
Hourly Load 33KV C8 FDR — —
Hourly Load 33KV C9 FDR — —
Hourly Load 33KV CEMENT FACTORY FDR — —
Hourly Load 33KV CERAMICS FDR — —
Hourly Load 33KV FDR D3 — —
Hourly Load 33KV FDR D4 — —
Hourly Load 33KV FDR D5 — —
Hourly Load 33KV FDR GL33 — —
Hourly Load 33KV FDR GL36 — —
Hourly Load 33KV GANFENG-PENSTOCK FDR — —
Hourly Load 33KV GOODER TECH PLUS FDR — —
Hourly Load 33KV LUGBE FDR — —
Hourly Load 33KV OKPELLA TOWN FDR — —
Hourly Load ADOGO — —
Hourly Load AGWARA — —
Hourly Load ALIERO — —
Hourly Load ANYIGBA — —
Hourly Load ARGUNGU — —
Hourly Load ARMY BARRACK — —
Hourly Load ASCO 132KV — —
Hourly Load AUCHI — —
Hourly Load Al-Hassin Company — —
Hourly Load BIRIGIFDR — —
Hourly Load BUNZA — —
Hourly Load CCNN — —
Hourly Load CEMENT FACTORY — —
Hourly Load CERAMICS — —
Hourly Load CONFLUENCE — —
Hourly Load EVENT — —
Hourly Load Emergency — —
Hourly Load FADAMA 2 — —
Hourly Load FADAMA1 — —
Hourly Load FARFARU — —
Hourly Load FDR1 — —
Hourly Load FDR2 — —
Hourly Load FDR3 — —
Hourly Load FEEDER 1 — —
Hourly Load FEEDER 6 — —
Hourly Load Forced — —
Hourly Load GAYA — —
Hourly Load GRA 11kv fdr — —
Hourly Load GWANDU — —
Hourly Load HYDROPOLIS 1 — —
Hourly Load HYDROPOLIS 2 — —
Hourly Load I — —
Hourly Load I/S — —
Hourly Load J/Bachita — —
Hourly Load JEGA — —
Hourly Load KOKO — —
Hourly Load KWARE — —
Hourly Load LABANA — —
Hourly Load Life Camp — —
Hourly Load M/KUNKEL0DR — —
Hourly Load MASUGA FDR — —
Hourly Load Mokwa — —
Hourly Load NEW INJECTION — —
Hourly Load NGASKI — —
Hourly Load OKPELLA TOWN — —
Hourly Load P/ HOUSE — —
Hourly Load P/STATN — —
Hourly Load SPARE-II FDR — —
Hourly Load STEELPLANT — —
Hourly Load TAMBUWAL — —
Hourly Load Town 11KV fdr — —
Hourly Load UNIVERSITY — —
Hourly Load YABO — —
Hourly Load YAURI — —
Hourly Load ZURU — —